Table 1.  Error in total mass predicted by GreenStar® versus weigh tank scale.

Target Flow

Run Time

 GreenStar® Total #1

 Scale Total #1

Error Test #1

 GreenStar® Total #2

 Scale Total #2

 Error Test #2

 Actual Flow 1

 kg/s

sec

kg

 kg

 %

 kg

 kg

 %

 kg/s

 1.3

 600

 795

771

 3.1

 792

 770

 2.8

 1.28

 2.1

 420

 904

900

 0.4

 906

 894

 1.3

 2.14

 4.2

 180

 810

798

 1.5

 797

 770

 0.9

 4.35

 8.4

 180

 1552

1554

 0.1

 1505

 1514

 0.6

 8.52

 12.7

 180

 2322

2329

 0.3

 2261

 2248

 0.6

 12.71

 16.9

 120

 2063

2067

 0.2

 2038

 2007

 1.5

 16.97

 21.1

 120

 2502

2573

 2.7

 2581

 2512

 2.7

 21.19

1. The actual flow is calculated using the average total mass accumulated at the weigh scale divided by the number of seconds that the meter was delivering grain to the clean grain elevator.